CURRENT PROJECTS

Marketplace @ 249

Description: A 34-acre commercial development has been completed for multiple commercial properties. Developments are anticipated to include grocery stores, fast food restaurants, banks, and retail centers. Utility and drainage construction has been completed.

Commercial developments to come:

  • Starbucks
  • Jersey Mikes
  • Chipotle

Water Plant No. 5

Description: The District is actively looking for a site to construct Water Plant No. 5. This plant will consist of a water well, ground storage tank, hydropneumatic tanks, booster pumps and a control building

  • Status: Acquiring tract.
  • Start Date: October 2022
  • Completion Date: October 2024

Deer Ridge Water Plant Booster Pump Addition

Description: The District is adding a booster pump at the Deer Ridge Water Plant. This addition will help keep the pressure consistent within the system.

  • Status: Near Completion
  • Start Date: April 2022
  • Completion Date: December 2022

Lift Station Discharge Improvements

Description: The District is adding a booster pump at the Deer Ridge Water Plant. This addition will help keep the pressure consistent within the system.

  • Status: Near Completion
  • Start Date: April 2022
  • Completion Date: December 2022

COMPLETED PROJECTS

Fallbrook Drive Lighting

Description: The District is working with Harris County and Centerpoint Energy to provide street lighting along Fallbrook Drive. The plans have been submitted to the governing agencies.

  • Status: Under Design
  • Start Date: Completed
  • Completion Date: Completed

Northwest Park, Sections Six & Seven Sanitary Sewer Rehabilitation

Description: The Sanitary Sewer Collection system within Northwest Park, Sections Six & Seven are being scheduled for a cleansing and televising. Video footage will show if there is are significant repairs needed due to the age of the pipe, including protruding roots, debris and grease deposits that block a portion of the flow, decreasing the capacity within the line. Once the line televising is complete, the rehabilitation will proceed.

  • Status: Awaiting completion of televising
  • Start Date: Mid 2021
  • Completion Date: Late 2021