Northwest Park Municipal Utility District continually undertakes projects to improve and maintain the water supply and wastewater collection facilities in the district. See current and future projects below:

Current Projects

  • Northwest Park, Sections Six & Seven Sanitary Sewer Cleansing & Televising
    Description: The Sanitary Sewer Collection system within Northwest Park, Sections Six & Seven are being scheduled for a cleansing and televising. Video footage will show if there is are significant repairs needed due to the age of the pipe, including protruding roots, debris and grease deposits that block a portion of the flow, decreasing the capacity within the line.
    Status: Project is under design
    Start Date: November 2020
    Completion Date: February 2021
  • Water Plant No. 5
    Description: The District is actively looking for a site to construct Water Plant No. 5. This plant will consist of a water well, ground storage tank, hydropneumatic tanks, booster pumps and a control building.
    Status: In discussion with various land owners
    Start Date: Unknown
    Completion Date: Unknown

Future Projects

  • Northwest Park, Sections Six & Seven Sanitary Sewer Rehabilitation
    Description: The Sanitary Sewer Collection system within Northwest Park, Sections Six & Seven are being scheduled for a cleansing and televising. Video footage will show if there is are significant repairs needed due to the age of the pipe, including protruding roots, debris and grease deposits that block a portion of the flow, decreasing the capacity within the line.
    Once the line televising is complete, the rehabilitation will proceed.
    Status: Awaiting completion of televising
    Start Date: Mid 2021
    Completion Date: Late 2021

Completed Projects

  • Marketplace @ 249
    Description: A 34-acre commercial development has been completed for multiple commercial properties. Developments are anticipated to include grocery stores, fast food restaurants, banks, and retail centers. Utility and drainage construction has been completed.
    Commercial developments are actively looking at the site for development.
    Status: Complete
  • Fallbrook Drive Lighting
    Description: The District worked with Harris County and Centerpoint Energy to provide street lighting along Fallbrook Drive.
    Status: Complete